Rack density sets the schedule on a training campus, and it does so before the first footing is poured. A hall that holds racks of accelerators needs more power per square foot, more heat rejection per square foot, and often liquid delivered to the rack, so the mechanical and electrical rooms are no longer support spaces. They are the building. Everything we do on an AI training campus begins with the cooling method and the electrical block size, and the shell is drawn to suit.
Oklahoma is already seeing proposals at that scale. News coverage in September 2026 described four proposed data center campuses in Enid with developers estimating up to $35 billion in capital investment, though rezoning had been filed for only two sites and the city had given no approval at the time. A campus of 506 acres west of Owasso in unincorporated Tulsa County near an industrial park has been reported as another site. These are announced or proposed projects, not our work, and we mention them as evidence of the size of the opportunity and the questions that come with it.
A training campus asks different things of a builder than a conventional cloud site. Loads are steady and high, outages are expensive, the building may be sold or leased as a unit, and the technology inside will change faster than the shell. We plan for that by leaving space and structure for the next cooling generation.
We work back from the heat. If the owner plans direct-to-chip liquid cooling, the building needs pipe racks, leak detection, a secondary loop and a way to drain and fill. If the plan is rear-door heat exchangers or immersion, the floor loading and the maintenance clearances change again. Our service for liquid cooling infrastructure coordination exists because those decisions touch the slab, the roof, and the central plant at once.
The same logic applies to power. A training hall draws near its design load for long periods, so the electrical rooms are sized and ventilated for continuous duty, and the pathways are routed to avoid mixing high-voltage and low-voltage cable. For owners who want a purpose-built hall, see our AI high-density data halls service.
Training campuses chase cheap, abundant power. Oklahoma Department of Commerce data states that renewables generate 47% of the state's electricity, that the state produces 61% more energy than it uses, that energy costs run 17% below the national average, and that the Traverse Wind Energy Center is 998 MW. In the northwest, federal energy data lists wind farms in Woodward County at 148.4 MW and 198.6 MW of nameplate capacity, and we treat those listings as context only, since power purchase terms are between the owner and the utility.
What matters for a builder is where the owner will connect. A campus beside a wind corridor may sit far from the load center, and the substation and transmission work can be as significant as the buildings. In Sand Springs, a city council reportedly approved an 827-acre data center on annexed land about eight miles north of downtown, with construction planned from 2027 to 2029, and that kind of timeline suggests how long utility work may take on any large site.
Three items dominate: electrical gear, cooling equipment and the interconnection. Transformers, switchgear and generators have the longest lead times, and the owner who orders late pays for it twice, in premium and in delay. Cooling plant sizing is next, since a design for liquid cooling at the rack still needs heat rejection to the outside.
The building itself is a smaller fraction than owners expect. That is why we favor a simple, buildable shell, such as tilt-wall or precast panels, and keep the expensive thinking in the mechanical and electrical rooms. We avoid quoting dollars per megawatt because it depends on design choices the owner has not made yet.
Cooling water is a siting question first and a construction question second. The Oklahoma Water Resources Board maintains a water permit process and a pending water use permits dashboard, and its home page points to a $24 billion water infrastructure need statewide. A campus that plans evaporative cooling should expect questions about source, volume and discharge. Closed-loop and dry cooling reduce water demand but raise power demand, and we model both for the owner.
Seismic activity is a second question. The two largest recorded Oklahoma events are the 2016 Pawnee earthquake at magnitude 5.8 and the 2011 Prague earthquake at magnitude 5.7. We design equipment bases, piping supports and bracing for the seismic category the engineer of record sets, and we ask for a geotechnical report before the pad is final.
A training campus is more than data halls. It includes a central utility plant, a battery energy storage yard where the owner wants ride-through for grid events, and an operations building. Each has its own permit path and its own commissioning sequence, and we build them on a master schedule so the energization dates work together. Owners buying from AI and GPU cloud operators sit at the other end of that chain, and they usually want a handover with test data they can show their own customers.
Send us the target density, the cooling approach and the date the utility says power can arrive. We will respond with a shell and yard plan and a list of the decisions that must be made first.
Yes, and most are. The usual pattern is to build common infrastructure and the first halls, then add halls as the utility delivers more power. Duct banks, yard space and structural provisions for later phases should be built in the first phase.
It changes the roof and slab loading, the pipe routing, the floor drains and the leak detection. It also raises the importance of commissioning. We coordinate with the mechanical engineer early so the structure reflects the final piping layout.
We help owners with early budgets and site feasibility, but we do not start construction until zoning, utility and water approvals are in place. A proposal for a campus may be rezoned, reduced or shelved, so we plan conservatively.
Get the utility's interconnection feasibility study, a geotechnical report and a water source letter. Those three documents set the site's real limits. We can then size the first phase and sequence long-lead procurement.
Yes. Many operators arrive with a prototype hall. We build to their drawings, offer constructability review, and follow their commissioning process.

Tell us about the site, the power and cooling plan and the schedule, and we will set up a review of scope, schedule, permits and inspections.