A two-million-square-foot building on a 2,000-acre park changes what "site work" means. When one operator announced a $1 billion hyperscale facility at an industrial innovation park in east Tulsa, with more than 1,000 construction jobs expected at peak, the headline was the building. For the builder the real story is everything around it: the roads that carry the peak workforce, the utility corridors that cross the park, and the batch plants and laydown fields that have to exist before the first slab is poured.
Hyperscale work in Oklahoma is a different problem from enterprise or colocation work because the unit of delivery is a campus, not a hall. A single building may be repeated four times, as in the multi-phase north Tulsa County campus reported at up to four facilities and close to 1.2 million square feet, with the first phase scheduled for summer 2027. The repeatable parts (shell geometry, slab details, roof system, generator and cooling pads) should be solved once and priced as a template. The parts that vary by site (soil, drainage, utility feeds, access) get their own scope.
We work with the utility and the county early, because power and water decide the site. On a hyperscale parcel that conversation starts before the first drawing is final. This page describes how we approach a hyperscale data center in Oklahoma, from the shell and slab to the yards and the interconnection that makes the building worth operating.
The attraction is energy. The Oklahoma Department of Commerce reports that the state produces 61% more energy than it consumes and that energy costs run 17% below the national average. For a campus that will draw continuously for years, a lower power cost and a deep generation base matter more than almost any other siting input, and they explain why large parcels outside the metros are being assembled for data center use.
Oklahoma also offers land at industrial scale. MidAmerica Industrial Park near Pryor is described as the state's largest industrial park at 9,000 acres, with electricity supplied through the Grand River Dam Authority, and a public report put one operator's total investment there at $4.4 billion with more than 800 people in full-time and external supplier roles. Whatever your own site is, those numbers show how the market has already absorbed a very large mission-critical footprint. We read them as evidence that hyperscale cloud providers will keep returning to the state, and we plan crews and procurement accordingly.
The core of the package is the data hall building: a long, wide, single-story or two-story shell with a heavy roof load and a slab built for dense equipment. Most operators in this size class favor tilt-wall and precast shells because panels can be cast on site and set quickly, which keeps the dry-in date close to the notice to proceed. Structural steel is added where the roof must carry mechanical equipment or long spans.
Around the building we build what makes it a campus. That means the electrical service entrance and duct banks, the generator and fuel yard, chiller or air-cooled pads, a security perimeter, stormwater detention, and truck courts sized for equipment deliveries. The on-site substation yard is often the longest single item in the package, and we plan it as its own work package with its own critical path.
Oklahoma has no state general contractor license, but trade work (electrical, mechanical, plumbing) is licensed through the Construction Industries Board, so our trade partners hold the credentials the work requires. The state commission adopted newer International Codes, and the state-adopted National Electrical Code applies. Cities adopt and enforce their own editions, though. The City of Tulsa lists the codes with local amendments and has an ordinance update pending, so a campus may sit across an edition change.
Our practice is to confirm the edition with the building department before the permit set is issued, record it in the drawings, and keep a written record of any local amendment. For a hyperscale owner that is cheaper than a late reissue of a structural package.
Cost on a campus follows repetition and power. Repeat buildings let us carry learning from one structure to the next, so the first building usually costs more per square foot than the third. The drivers that do not repeat are the site: depth to competent bearing material, the volume of cut and fill, how far the utility feed must travel, and how much stormwater detention the creek basin requires.
Long-lead electrical gear is the other big swing. Transformers, switchgear and generators can govern the schedule well beyond what the concrete does, and we advise owners to treat long-lead equipment procurement as part of preconstruction, not a post-award task. We do not publish price-per-square-foot figures because they would mislead; we price from drawings and the owner's equipment list.
Peak labor is the constraint. A project that expects more than 1,000 construction jobs at its busiest moment needs parking, a safe site access plan, badging, and a way to feed and move people. We build the temporary roads and parking early and phase the building so trades do not stack on one another.
We also plan around weather. Oklahoma averages about 59 tornadoes a year, with May the peak month, and we schedule steel erection, roof work and panel lifts with that season in mind. On large tilt-up pours we hold wind and lightning protocols and keep a practical stand-down plan, because a lost day on a four-building campus ripples through every following phase.
Most hyperscale buyers need more than one of our services at once. Hyperscale campus construction covers the whole delivery, while mass grading and site development can be contracted first to prove out the pad. For owners who want to understand the next stage of density, our AI training campus page explains how liquid cooling changes the scope, and the Tulsa page describes how we work in the metro where several of these announcements are located.
Share the site boundary, the utility's feasibility letter and a target in-service date. We will return a phasing outline, a list of the long-lead items to order first, and a plain statement of what we cannot yet confirm.
It depends on how much of the campus is ready when the notice to proceed arrives. One announced east Tulsa facility is expected to be operational in 2028, and another north Tulsa County campus lists a first-phase target of summer 2027. Those dates include utility work and fit-out, not just the shell. We outline a schedule from the site and equipment lead times, then update it as the interconnection date firms up.
Utility interconnection and any rezoning or annexation usually lead, followed by water and stormwater permits. In Oklahoma the permitting authority varies by parcel: some land is in a city, some is unincorporated county land, and the code edition follows the jurisdiction. We ask the county and the utility for their review calendars before we promise a start date.
Yes, with controls. We separate construction traffic from operating access, keep dust and vibration away from live halls, and coordinate shutdown windows for any tie-ins. A phased plan with a defined energization sequence is easier on both the owner and the utility.
Tornado exposure, variable soils that change from parcel to parcel, flooding near creeks and river levees, and in some areas induced seismicity. We design roof, equipment anchorage and drainage with the local record in mind and ask for a geotechnical report early.
Both. We work from an owner's prototype when the operator has one, and we provide design-build delivery when the owner wants a single point of responsibility.

Tell us about the site, the power and cooling plan and the schedule, and we will set up a review of scope, schedule, permits and inspections.