Cooling decides the footprint of a data center, and in Henryetta the first cooling question is where the water comes from and where it goes. The town draws its public drinking water from Jim Hall Lake, also called Lake Henryetta, which covers 450 surface acres southeast of town. A data center owner cannot treat that lake as a free supply. Any cooling design here should begin with a conversation with the city about capacity and priority, and with a plan that uses as little potable water as the equipment allows.
We build mechanical yards for owners who want that conversation early. A yard includes the chiller or dry-cooler pads, pumps, piping, controls, makeup water and the access that keeps it all serviceable. The choice between air-cooled, water-cooled and hybrid plant changes the pad size, the electrical load, the water demand and the noise at the property line. We present these tradeoffs in plain numbers, and we write down the assumptions behind each one, with the cost of each option over a typical ownership period, so the owner can choose with clear eyes.
Henryetta is at the crossroads of Interstate 40 and US-75, a location that helps both the delivery of heavy mechanical equipment and the range of trades available to install it. Chiller plant is heavy and slow to ship, so route and timing questions come up in the first meeting.
Cooling equipment has some of the longest lead times on the job, and underground piping and pads must be finished before it arrives. We schedule excavation, pad placement and underground utilities so that a chiller can be set the week it reaches the site. Setting it early is as costly as setting it late, because stored equipment needs protection and its warranty clock may begin.
Interstate 40, US-75, US-266 and Oklahoma State Highway 124 serve the town, so oversize loads have several approaches. We choose the route after checking bridge ratings, turning radii and permit rules.
The Indian Nation Turnpike finishes its 105-mile run from Hugo at the interstate here, so equipment bound for the southeast part of the state can leave the interstate here and use a divided highway. We note that option in the delivery plan whenever a unit is large enough to need a permit.
A closed-loop air-cooled plant uses almost no water but draws more power. A water-cooled plant uses less power but needs makeup water, treatment and blowdown handling. A hybrid design runs dry in cool weather and uses water in heat. We model each against the utility's capacity, the climate and the owner's cost of power and water.
Noise also enters the choice. Large air-cooled plants make sound at the property line, and fans can be specified to run slower, enclosed or screened by walls. We ask the city about limits and the neighbors about concerns before the layout is final, because a sound complaint after startup is expensive to fix.
Our chiller and cooling plant pads and liquid cooling infrastructure coordination services support those choices, from the pad to the pipe to the manifold at the rack.
The yard scope begins with grading and drainage, then reinforced pads, trenches for pipe and power, equipment setting, piping, insulation, controls and fencing. We manage the trade partners who do each task and inspect pressure tests, welds and insulation before the work is covered.
Where the owner wants a reuse line or a water source other than the city, cooling water supply and reuse lines covers the pipe, pumps and connections, subject to the permit and the supplier's agreement.
Water treatment is part of the scope too. Chemical feed, filtration and drainage need space and a safe way to handle chemicals, and the owner's operators need training on testing and logs. We include the skids, containment and signage in the yard design rather than leaving them for the operator to add.
Henryetta's employers include a glass container plant that has operated for almost 100 years on the former site of a plate glass factory, a company serving the oilfield and a maker of shipping pallets. A report dated February 6, 2026 said that state commerce staff toured the glass plant, which runs one of the largest glass melting furnaces in the world. Heavy industry nearby means truck traffic, heat, noise and utility loads that a new neighbor should expect, and it shows that the town is used to industrial construction. We still ask the electric provider what capacity a parcel can receive, since industrial neighbors do not guarantee spare service.
Plan for the dust and heat of nearby industry when choosing filters, louvers and coil coatings, because outdoor air quality affects how often equipment needs cleaning. We include filter access and washdown provisions where the site calls for them.
The yard is not finished when the equipment is set. Commissioning proves that flow, temperature, controls and alarms respond as designed, and the results become part of the turnover record. Our integrated systems commissioning page lists the tests.
Power developers and large enterprise users evaluate cooling cost as a share of operating cost. The utilities and power developers page shows how a mechanical plant ties into the electrical design, and the hyperscale cloud providers page explains how larger users approach water. Each owner type weighs the tradeoffs differently, and a tenant may impose its own standards that we build into the specification.
Owners who also consider Bixby or Jenks can ask us to compare cooling designs and water availability at each.
Share the load and the water options you have. We will compare plant types, estimate pads and piping and outline the commissioning plan.
Possibly, but the city decides capacity and priority, since its drinking water comes from the lake. We ask early, and we design a plant that limits potable water use through closed-loop, hybrid or reuse options.
An air-cooled closed-loop plant uses almost none, but it uses more electricity and larger pads. We compare it with water-cooled and hybrid plants for the owner's load, climate and utility rates.
It depends on capacity and plant type. We draw the yard with service clearances, pipe routes, crane reach and room for added equipment. A future expansion should be able to roll in without disturbing live units.
It proves flow, temperature, control response and alarms under real load, including failure cases such as a pump trip. Results are recorded and handed to the operator.
Yes. Pumps, valves, chillers and controls are tested individually, then together, then under simulated failures. The tests happen on a published schedule, and the operator attends so that procedures match the installed equipment.
The interstate and US-75 junction offers heavy-haul approaches. We check bridge limits, turns and permits for each large unit before setting a date.

Tell us about the site, the power and cooling plan and the schedule, and we will set up a review of scope, schedule, permits and inspections.